RESOLUTION NO. 2001–03
A RESOLUTION OF THE SAN
BENITO COUNTY WATER DISTRICT
ESTABLISHING A POLICY FOR
INTER-SUBSYSTEM WATER TRANSFERS
FOR THE 2001-2002
CONTRACT WATER YEAR
WHEREAS,
the Water Users’ Handbook, Rules and Regulations for delivering and receiving
San Felipe Distribution System Water requires the annual review of terms and
conditions governing inter-subsystem transfers; and
WHEREAS,
the Annual Groundwater Report for the 1999-2000 Water Year presented facts and
the basis for findings that certain groundwater sub-basins are experiencing
high groundwater levels; and
WHEREAS,
inter-subsystem transfers from subsystems experiencing elevated groundwater
levels to subsystems which are currently under supplied and/or have available
groundwater storage could serve to mitigate the potential impact of elevated
groundwater levels; and
WHEREAS, it is anticipated the
District will receive an allotment of 65% Agricultural water and 85% Municipal
and Industrial water,
NOW,
THEREFORE the Board of Directors of the San Benito County Water District
hereby resolves that:
Authorization for inter-subsystem
transfers shall be subject to the following conditions which were designed to
mitigate potential impacts on well users in the groundwater basin from which
water is being transferred and to mitigate the potential impacts on lands
within high groundwater areas.
1.
Any such
inter-subsystem transfer shall not cause any unreasonable impact on the water
supply, operation, or financial condition of the District.
2.
Any
administrative costs incurred by the District in order to facilitate the
transfer shall be paid by the transferee.
3.
All
project water transferred between subsystems shall be considered “Class 2
Water”, which is defined to mean all water over and above that originally
allocated the land by the District, and which is otherwise eligible for
transfer.
4.
All water
originally allocated to the land (Class 1 Water for purposes of this
resolution) shall be beneficially used before Class 2 Water may be transferred
between the subsystems.
5.
No Class
2 Water shall be considered for repurchase by the District.
6.
No
inter-subsystem transfer shall be permitted into Subsystems 1, 1A, 2, 3, 4, 5,
10 and 11.
7.
Inter-Subsystem
transfers from Subsystems 6, 7 and 9 shall be subject to the following
additional conditions.
a.
A
transferor shall not transfer more than 30% of the project water available to
any one parcel of land.
b.
Out of
the total amount of project water authorized for transfer between a subsystem,
25% of such water shall be paid for, deducted from the total allocation, and
percolated into the groundwater basin from which the water is being
transferred.
THE
FOREGOING RESOLUTION
was adopted at a regular meeting of the Board of Directors of the San Benito
County Water District held on the 24th of January, 2001.
AYES: DIRECTORS Swanson, Tobias, Perry, Keck, DeLaCruz
NOES: DIRECTORS None
ABSENT: DIRECTORS None
_________________________________
Robert
Swanson
President
ATTEST:
________________________________________
Janet L. Miller
Administrative Services Officer